Bandar Abbas Refinery
BANDAR ABBAS REFINERY (Increasing the capacity of Gasoil Production)
CONSTRUCTION of COOLING TOWER (EPCC)
Project Details:Owner: National Iranian Oil Engineering & Construction Company (NIOEC) Project Location: Petrochemical Industries Design & Engineering Company (PIDEC) Project Location: Bandar Abbass (Reinery) Capacity: 10,000 m3/h Technical Category: Oil & Gas (Refinery) Stakeholders: HAMON (Main Vendor), Mather & Platt Project Status: Completed (Under Operation) |
|
Responsibility:Detail engineering, procurement, construction and commissioning of Cooling Tower for Bandar Abbass refinery for the purpose of increasing gasoil production capacity of the same. Main Features: Circulation water: 10,000 m3/h No. of cells: 4 cells, (2500 m3/h each) No. of pumps: 2 turbine pump (2500 m3/h each), 2 electrical pump (2500 m3/h each) |